PROJECT 03 · PEAK SHIFTING

Peak Shifting

A two-phase battery system and 6.45 MW PCS designed for two daily Time-of-Use cycles at a high-load refinery.
Chenzhou, China
Location
Chenzhou, China
Fengyue Metal Refinery
CLIENT
Fengyue Metal Refinery
33.44 MWh BESS
SYSTEM SCALE
33.44 MWh BESS
The two-phase battery installation at the refinery site.
Overview
Fengyue Metal Refinery is a local smelting plant in Chenzhou. Its machinery requires high power output and the factory consumes approximately 50 MWh of electricity per day. The peak-shifting system moves energy use across Time-of-Use windows to reduce operating cost while supporting continuous industrial production.
Client Request

01.     Support daily energy consumption of 52 MWh.

02.     Run two Time-of-Use cycles per day.

03.     Capture a US$0.10 difference between peak and low-tariff periods.

04.      Shorten the investment payback period.

Project Solution

—     Phase 1 battery system — 8.36 MWh (418 kWh × 20; 166.4 V / 314 Ah × 8 units × 20)

—     Phase 2 battery system — 25.08 MWh (418 kWh × 60; 166.4 V / 314 Ah × 8 units × 60)

—     PCS — 6.45 MW (2,150 kW × 3 units)

Reported Outcomes

Approximately US$2 million in annual electricity-cost savings.
2.5-year investment payback period.

Site View

Indoor storage units supporting the Time-of-Use operating cycles.